Before mood boards or material palettes, every Dubai interior project needs a structural decision: who is responsible for the drawings, and who is responsible for what gets built from them. This guide compares design-only and design-and-fit-out contracts by scope, defects, programme and permitting, and sets out the questions to settle before you sign.

By Abdallah Massarweh, Co-Founder & Operations Director ·

The real decision is about risk, not style

Most owners frame the choice as a question of taste. The choice that actually shapes cost, programme and recourse is which party holds design responsibility and which holds delivery responsibility.

A design-only appointment buys drawings, specifications and design intent. A design-and-fit-out contract buys a finished space, with one party answering for both the drawing and the work built from it.

A quick test before you sign: if something is wrong at handover, who do you call? If the answer is not obvious, the contract structure needs more work.

What a design-only appointment usually covers

Scope varies from firm to firm, so read the fee proposal line by line. A complete design-only appointment typically includes:

What it usually excludes: construction labour and materials, the contractor's programme, snagging, the defects liability period and any warranty on the built work.

What a design-and-fit-out contract adds

In a design-and-fit-out (design-and-build) contract, one company produces the design and builds it. On top of the design scope above, it takes on:

The trade-off: because design and build are not tendered separately, you lose competitive pricing on construction, and the independent check between designer and builder disappears unless the contract puts one back.

The seam between drawing and site: who owns a defect?

When design and delivery sit with separate firms, the gap between the drawing set and the built work becomes the owner's problem first.

Protect yourself in writing: a responsibility matrix, an agreed substitution procedure, one route for reporting defects, and a named party who reviews the contractor's shop drawings against the design. Whether the contract promises a result fit for its purpose, or only reasonable skill and care, is worth confirming with your legal adviser before you sign.

Where programme and variation risk land

Under design-only, construction programme risk sits between you and your contractor. A change can bite twice: once as a design fee to revise the drawings, and again as the contractor's variation for the work it triggers. Long-lead items such as imported finishes, joinery and specialist equipment can move handover if nobody commits the order dates.

Under design-and-fit-out, one party owns the completion date, design period included, and a design change and its construction cost can be priced together. That certainty is usually reflected in the price.

Whichever model you choose, ask three questions: who carries the completion date, what happens if it slips, and how are variations priced and approved?

Permitting: where the Architect of Record sits

Approvals are a separate scope in Dubai, not a free extra. Depending on the property, a project can involve Dubai Municipality, the Dubai Development Authority, Trakhees, Dubai Civil Defence and the master developer. Which authority approves your project depends on the community and zone your plot sits in, and it's confirmed from your plot documents. See examples by community.

The Architect of Record is the licensed firm that takes legal responsibility for submissions to the authorities, secures the permits and signs off the construction stage. If your designer is not the Architect of Record, another firm is, and that firm now sits inside your approval chain and your programme. A design-and-fit-out contract does not settle this automatically: confirm in writing who acts as Architect of Record and who obtains the master developer NOC.

When approvals sit outside every contract, they sit with you: chasing NOCs, answering authority comments and resubmitting.

A third route: one studio for design, permitting and supervision

There is a middle path between the two models, and it is how Ganggaan works. One studio designs the space, acts as Architect of Record for the approvals, sources the FF&E, and then prequalifies, tenders and supervises the contractor on your behalf.

The contractor still builds and still carries its own obligations for defects. The difference is that one accountable studio manages the seam between drawing, approval and site. See how this works on our project management and site supervision and renovation and fit-out pages.

How to choose

Whichever you choose, write the responsibility matrix into the contract. Design, approvals, procurement, site supervision, handover and defects should each name one party. If it is not written down, it is not allocated.

Not sure which authority covers your plot? Send us the community or plot number and we'll tell you. Message us on WhatsApp or use the contact form.

Frequently Asked

Common questions

Is a design-only contract cheaper than design-and-fit-out in Dubai?

The professional fee looks lower, but coordination, rework and delay costs can surface later. Compare the total cost across the whole programme, including who manages the contractor and the approvals, not the design fee alone.

Does a design-only fee include authority permits?

Only if the proposal says so. Many design-only fees stop at drawings. If permitting is not listed, budget separately for an Architect of Record and for the approvals.

Who should be the Architect of Record on an interior project?

Ideally the team that drew the design, because it is best placed to answer the authorities' comments on it. Confirm in writing who it is before you sign, because that firm sits inside your approval chain and your programme.

Can Ganggaan supervise a build designed by another firm?

Yes. Ganggaan regularly supervises builds where the design was done by another firm, including international designers, and protects that design through construction.